Skip to Main Content

Use the Sunbelt Rentals app

Find, rent, and return equipment, right at your fingertips

A custom pumping solution at a wastewater treatment facility.

Custom Pump System Design Prevents Service Interruption at Major Wastewater Facility

When one of Kentucky's largest wastewater treatment facilities needed to replace their aging pump station, Sunbelt Rentals helped engineer and implement a custom temporary pumping solution to maintain essential operations. Through innovative design and close collaboration with the engineering firm, the project successfully bridged the gap during the year-long construction of permanent facilities.

Project at a Glance

A major municipal wastewater treatment plant required a temporary pumping solution during the construction of a new pump station. The project demanded careful coordination between multiple stakeholders and custom equipment design to handle flows between 7 and 14 million gallons per day within existing infrastructure constraints.

Scope

Design, engineer, and install custom pumping systems to maintain treatment plant operations during pump station replacement.

Goal

Maintain uninterrupted wastewater treatment operations throughout a 12-month construction project.

Solution

Provided an integrated custom pumping solution with advanced control systems, backed by engineering expertise and 24/7 technical support.

Equipment

  • · Custom-Engineered High-Capacity Pumps
  • · VFD Control Panels
  • · Specialized Suction and Discharge Piping

Results

Met aggressive 16-week design-to-installation timeline. Successfully maintained facility operations throughout construction while enabling complete pump station replacement with zero service interruptions.

Challenge: Engineering Within Unique Geographic Constraints


Lexington's unique topography creates unusual demands on its wastewater infrastructure. Water flows away from the city in almost all directions, requiring more pump stations than typical municipalities of similar size. When the West Hickman Creek facility's aging pump station needed replacement, this geographic reality complicated an already complex situation.

 

The existing infrastructure presented significant limitations. Two parallel 60-inch sewers fed into a confined influent channel, making standard temporary pumping solutions impossible. Initial plans called for electric submersible trash pumps, but the space simply couldn't accommodate equipment large enough to handle the flow requirements.

 

 

Set-Up: From Custom Designed Pumps to Implementation


The primary challenge became clear early in the project — this wasn't a standard rental situation. Sunbelt Rentals worked directly with the facility's programming team to understand the integration requirements. The confined space demanded custom-engineered pumps that could handle substantial flows while fitting within strict dimensional constraints.

 

Three overflow incidents during the early phases helped refine the design. After several design iterations, the team settled on a solution that positioned the pumps at the lowest possible elevation for optimal suction lift, leading to additional redundancy measures in the final implementation.

 

 

A custom-engineered pump system in a confined space.

 

Solution: Meeting Time-Critical Requirements


With just 16 weeks from initial concept to installation, Sunbelt Rentals coordinated closely with the facility's engineering firm, Hazen and Sawyer, throughout the manufacturing process. The solution centered on custom-built pumps integrated with sophisticated controls that connected directly to the plant's existing SCADA system.

 

The control system integration made a significant difference. Plant personnel could monitor the wastewater treatment temporary pump equipment using their own facility's interfaces. This familiarity allowed for seamless operation throughout the construction period.

 

 

A custom-engineered pump system in a confined space.

 

 

Results: Keeping Wastewater Treatment Running During Infrastructure Upgrade


The temporary system bridged the gap effectively during the construction of the new pump station. Treatment operations continued without interruption while construction proceeded on the permanent facility. Operators reported stable performance throughout the project. No service interruptions occurred. No overflow incidents emerged. This project’s wastewater temporary pump solution proved that smart engineering, combined with practical operations experience, could overcome even the most demanding infrastructure challenges.

 

 

Get Support

Need help with a complex municipal infrastructure project?

From custom equipment design to installation and 24/7 monitoring, our engineering team is ready to help solve your most challenging problems.