Use the Sunbelt Rentals app
Find, rent, and return equipment, right at your fingertips
Critical backup generator systems must undergo strict generator load bank testing and commissioning on a regular basis. In the healthcare industry, American Society of Healthcare Engineers has determined that facilities “must inspect their emergency generators” on a weekly schedule and test under load on a monthly schedule
System inspections should include fuel checks (main and day tank levels, day tank float switch, fuel pressure, and any obstructions to piping, hoses, or vents), oil checks, validation of cooling systems, exhaust systems, and battery systems, as well as prime mover and generator components. (NFPA 110, Sec. 6-4.1) The regulations outlined here, while applicable primarily in the healthcare industry, give insight into the kind of protocols established in other industries that require load testing for generator backup systems
Let’s review a healthcare industry generator testing and commissioning procedure example. In it, we will look at testing programs and protocols for how to load test a generator so that you can know what to expect before testing your generator project.
Every generator load bank testing operator should have a testing program in place that outlines the project’s goals and procedures. If we look at the healthcare industry’s use of load banks for generator testing, we find a good example of how testing and commissioning should follow explicit objectives, as well as an indication of optimal generator load bank testing frequency.
Having clearly defined objectives such as these enables testing teams to keep their focus and remain goal-oriented throughout complex testing sequences
Protocols for generator load bank testing of generators tend to shift from one industry to another. But for the most part, protocols follow industry best practices and are somewhat standardized as generators typically employ the use of only two out of the three main types of load banks. When conducted properly, comprehensive testing and commissioning will give contractors greater confidence in backup power systems.
Testing begins by starting and running the generator(s) until voltage stabilizes. Then automatic transfer switch is transferred to the emergency power source. The generator load can then be increased in steps that simulate expected in the facility.
Be sure to address any alarms or alerts, should they pop up.
For comprehensive load testing, the generator must run at or near rated capacity for several hours. After conducting the test, remove the load bank first and return all transfer switches to their original state. Follow manufacturer guidelines to cool down the generator(s). Finish by logging information about all aspects of the generator load bank test, including time of testing, test conditions, and load size.
Proper use of load banks when testing generator sets can have great benefits for electrical systems undergoing the testing and commissioning process or regularly scheduled maintenance. Using load banks can help improve efficiency and cost-effectiveness by:
As we have seen in the healthcare industry, following along a well-established set of goals and procedures ensures that any source of system failure, such as a faulty transfer switch or failed oil pump, can help system operators address issues before they arise in an emergency. In this case, testing and commissioning provides a controlled environment where a well-prepared staff can easily mitigate problems.